Installation of a back epiploon of a cranked shaft. BMW the 5th E28/E34 series (from 1981 to 1993 of release)
Repair of BMW E28 and series E34 from 1981 to 1993
1. Cars of the BMW brand of 5-series
2. Engine
2.1. The repair work which is carried out without extraction of the engine from the car
2.2. Procedures of major maintenance of components of the engine
2.2.1. General information
2.2.2. General information about major maintenance of the engine
2.2.3. Check of extent of compression
2.2.4. Ways of removal of the engine and precautionary measure
2.2.5. Removal and engine installation
2.2.6. Options of major maintenance of the engine
2.2.7. An order of dismantling of the engine at major maintenance
2.2.8. Dismantling of a head of cylinders
2.2.9. Cleaning and check of a condition of a head of cylinders and components
2.2.10. Service of valves
2.2.11. Assembly of a head of cylinders
2.2.12. Removal of pistons / rods
2.2.13. Removal of a cranked shaft
2.2.14. Removal and check of a condition of an intermediate shaft
2.2.15. Cleaning of the block of cylinders
2.2.16. Check of a condition of the block of cylinders
2.2.17. Honingovaniye of cylinders
2.2.18. Check of a condition of pistons / rods
2.2.19. Check of a condition of a cranked shaft
2.2.20. Check of a condition of radical and shatunny bearings
2.2.21. Engine balance of assembly at major maintenance
2.2.22. Installation of piston rings
2.2.23. Installation of an intermediate shaft
2.2.24. Installation of a cranked shaft and check of lubricant gaps of radical bearings
2.2.25. Installation of a back epiploon of a cranked shaft
2.2.26. Installation of pistons / rods in collecting and check of lubricant gaps in bearings of rods
2.2.27. Start and an engine running in after major maintenance
2.2.28. Diagnostics of malfunctions of the engine
3. Cooling system
4. Power supply system
5. Ignition system
6. Control systems of the engine and decrease in toxicity of the fulfilled gases
7. System of production of the fulfilled gases
8. Coupling
9. Manual box of gear shifting (RKPP) and automatic transmission (AT)
10. Transmission line
11. Steering and suspension bracket
12. Brake system
13. Body
14. Control body sizes
15. Heater and air conditioner
16. System of onboard electric equipment
17. Routine maintenance of the car
18. Size table and adjusting data
19. Schematic electric circuits
20. Governing bodies and operation receptions
21. System of onboard diagnostics - a principle of functioning and codes of malfunctions
 













2-2-25-ustanovka-zadnego-salnika-kolenchatogo-vala.html

2.2.25. Installation of a back epiploon of a cranked shaft

 PERFORMANCE ORDER

  1. At first it is necessary to establish a cranked shaft, then to tighten bolts of covers of radical bearings. Then in the holder establish a new epiploon and tighten bolts of fastening of the holder to the block.
  2. Before installation of a cranked shaft very carefully check a surface of contact to an epiploon about scratches and jags which can damage a fillet of a new epiploon and cause leakages of oil. If the cranked shaft is damaged, the unique alternative is other or new cranked shaft if in a mechanical workshop will not offer a way of repair.
  1. The old epiploon can be taken from the case by means of a hammer and a punch, influencing from the back party. Do not forget to pay attention before extraction, on what depth the epiploon is established in the case; the new epiploon should be established on the same depth. Be very careful not to scratch or put other damages to an opening in the case, differently there can be a leakage of oil.
  1. Be convinced that the holder pure, then put on the external region of a new epiploon a thin layer of impellent oil. The epiploon follows plainly задавливать in a case opening therefore application of a hammer is undesirable. If the press is inaccessible, clamp the case and an epiploon between two smooth whetstones of a tree and press an epiploon into place between sponges of a big vice. Whetstones of a tree should be rather thick that the effort was distributed evenly on all circle of an epiploon. Working slowly, being convinced that the epiploon plainly enters into a case opening.
  1. Before putting on the epiploon/holder a cranked shaft and to tighten bolts, it is necessary to grease fillets of an epiploon with universal greasing or pure impellent oil. Establish new laying - hermetic is not required, and before installation of the holder be convinced that directing pins are on the places.
  1. Gradually tighten nuts/screws of the holder while they will not be hardly wrapped up, tighten them with the effort specified in the Size table and adjusting data at the end of the Management.


«on page back
2.2.24. Installation of a cranked shaft and check of lubricant gaps of radical bearings
on page forward»
2.2.26. Installation of pistons / rods in collecting and check of lubricant gaps in bearings of rods